The plan for next 2 week will be to continue to export soils and to start opening up A wing and finish excavating for B wing. Underground plumbing and electrical will finish in C wing and move into B wing. Continue B wing frost walls and spread footings. Prep for steel delivery and hopefully start erecting steel toward the end of the next 2 weeks. I have attached the 3-week lookahead from H.V. Collins as well. I have also included the draft meeting minutes of the 12-4-2017 SBRC meeting. As always we keep adding all these items to the website. CMS-MA.com Lastly, I have included a photo from this morning showing the pile is all gone, we are just hauling out rocks and digging out the rest of B and A-wing. Have a happy holiday Kevin Griffin Project Manager 508.561.8712 cell 508.786.0600 Office 508.786.0608 Fax Hi All,
Due to the snow fall on Saturday, we will be plowing the site today once the snow finishes. No work will be taking place just snow clean up to avoid any delays. I have asked for the contractor to use trucks that do not have back up alarms but they could not guarantee what truck will be going to the site yet. As always please feel free to reach out to me with any concerns. Thank you. Great news. The soil removal has begun and has been going well so far.
As always, any questions regarding the project please contact me. Or visit our Web Site for information regarding this project: http://cms-ma.com/dedhamecec All,
I am reaching out to provide an update on the trucking/soils removal time line, we had some paperwork issues with the trucking that are being resolved. We anticipate trucking to start this week. I will send out an email this week to verify the exact start date. |