The plan for next 2 week will be to continue to export soils and to start opening up A wing and finish excavating for B wing. Underground plumbing and electrical will finish in C wing and move into B wing. Continue B wing frost walls and spread footings. Prep for steel delivery and hopefully start erecting steel toward the end of the next 2 weeks. I have attached the 3-week lookahead from H.V. Collins as well. I have also included the draft meeting minutes of the 12-4-2017 SBRC meeting. As always we keep adding all these items to the website. CMS-MA.com Lastly, I have included a photo from this morning showing the pile is all gone, we are just hauling out rocks and digging out the rest of B and A-wing. Have a happy holiday Kevin Griffin Project Manager 508.561.8712 cell 508.786.0600 Office 508.786.0608 Fax Comments are closed.
|