CMS, INC.
  • Home
  • What We Do
  • Projects
    • Current Projects
    • Completed Projects
  • About Us
    • CMS Project Team
  • Markets
  • Contact

Project Updates

June 29, 2018

6/29/2018

 
Good morning.

In a continuing effort to keep the abutters of the new ECEC project apprised of construction activities, I wanted to reach out to inform you that the contractor has asked to work a small crew this Saturday June 30th We will do everything in our power to keep the noise to a minimum.

As always feel free to reach out to me with any concerns or questions.
Kevin Griffin
Project Manager
508.561.8712
508.786.0600​


June 22, 2018

6/22/2018

 
Good afternoon,

In a continuing effort to keep the abutters of the new ECEC project apprised of construction activities, I wanted to reach out to inform you that the contractor has asked to work a small crew this Saturday June 23rd. We will do everything in our power to keep the noise to a minimum.

As always feel free to reach out to me with any concerns or questions.
Kevin Griffin
Project Manager

508.561.8712 cell
​508.786.0600

Update for June 14, 2018

6/19/2018

 
All,


In a continuing effort to keep the abutters of the new ECEC project apprised of construction activities, I wanted to reach out to inform you of the process and procedure for upcoming Slab placements. We discussed the need for longer days at our kick-off meeting for activities like this as concrete has specific requirements for pouring, setting, and finishing. We anticipate this being the last concrete pour that will need extended hours as outlined below. Please know this is an approximate itinerary and times may exceed the times listed below or be shorter depending on how quickly the concrete hardens. When placing concrete slabs the ability to finish the slabs is critical to the process. The noise from 3 pm to 9 pm would be for the use of power trowels. The power trowels are a gas powered piece of equipment used to finish concrete. We will do everything in our power to keep the noise to a minimum.
6:00 am – We will begin setting up the pump truck
6:45 am – The first concrete truck arrives at the site
2:00 pm – the last concrete truck will be arriving at the site
3:00 pm – the pump truck will start breaking down
3:30 pm – the pump truck will be leaving the site
9:00 pm – the slabs will be finished and all powered equipment will be shut off*” This is the anticipated time this could be earlier or later depending on the workability of the concrete.”
10:00 pm – the gate will be locked and no one else will be on site
“We will be providing 48-hour notice to abutters prior to slab placement but the contractor is currently projecting a pour for 6-18-18”

As always feel free to reach out to me with any concerns or questions.

Kevin Griffin
Project Manager

508.561.8712 cell
508.786.0600

June 8, 2018

6/8/2018

 
Good afternoon,
In a continuing effort to keep the abutters apprised of the construction activities at the new ECEC Site. With the potential for good weather tomorrow 6-9-18 the contractor has asked to work Saturday to try and push the roofing work ahead. We have again asked them to keep all noises to a minimum. 
Please feel free to reach out to me with any concerns. 

Thank you,

​Kevin Griffin
508-561-8712
    < Back

    Archives

    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017

    Categories

    All
    Dedham ECEC News

    RSS Feed


Construction Monitoring Services
 Copyright © 2017
Construction Monitoring Services, Inc.
270 Main Street
Marlborough, MA 01752
T: 508-786-0600
F: 508-786-0608
Email: Info@CMS-MA.com
  • Home
  • What We Do
  • Projects
    • Current Projects
    • Completed Projects
  • About Us
    • CMS Project Team
  • Markets
  • Contact